Below are the appendices, end notes, and references for the paper The Bruce Highway Action Plan Program Evaluation.
| Project | Funding | Project Name | NPV ($) | BCR |
|---|---|---|---|---|
| C1 | BHAP | Cairns SAC Stage 3 – Kate St to Aumuller St | -77,213,044 | 0.03 |
| C3 | NB2 | Cairns SAC Stage 2 – Robert Rd to Foster Rd | 45,820,000 | 2 |
| C4 | BHAP | Edmonton to Gordonvale Duplication | -156,797,288 | 0.48 |
| C11 | BHAP | Townsville Northern Access – Intersections | -25,251,631 | 0.34 |
| C13 | NB2 | MacArthur & Melton Black Drives Intersection | 24,411,154 | 2 |
| C16 | BHAP | Bowen Intersection Upgrade | -25,713,888 | 0.04 |
| C19 | BHAP | Knobels Rd Intersection Upgrade | 6,000,000 | 2.2 |
| C20 | BHAP | Mackay Northern Access Upgrade - Stage 2 | -30,352,887 | 0.24 |
| C21 | NB2 | Mackay Northern Access Upgrade | 12,370,545 | 1.12 |
| C23 | NB2 | Mackay Intersection Upgrades Stage 2 | 13,610,000 | 2.4 |
| C24b | BHAP | Mackay Ring Road Stage 1 Construction | 606,633,413 | 2.35 |
| C26 | BHAP | Hay Point Road to Mackay Duplication | -218,508,625 | 0.44 |
| C27 | BHAP | Hay Point Road Intersection Upgrade | -15,145,614 | 0.43 |
| C28 | BHAP | Sarina to Hay Point Road Duplication | -191,770,422 | 0.34 |
| C29 | NB2 | Sarina Northern Access Upgrade - Coast Rd | -4,515,257 | 0.69 |
| C30 | BHAP | Rockhampton Northern Access Upgrade - S2 | -80,876,381 | 0.15 |
| C31 | BHAP | Rockhampton Northern Access Upgrade - S1 | -72,730,761 | 0.04 |
| C32 | BHAP | Rockhampton Intersection upgrades | -19,097,193 | 0.59 |
| C42 | BHAP | Tinana Interchange | 23,851,426 | 1.48 |
| C43 | BHAP | Wide Bay Highway Intersection (C45 built) | -44,268,686 | 0.11 |
| C43 | BHAP | Wide Bay Highway Intersection (C45 not built) | -39,240,964 | 0.22 |
| C44 | BHAP | Gympie Northern Approach Intersection Upgrades (Section D built) | -112,261,525 | 0.12 |
| C45/C46 | BHAP | Cooroy to Curra - Section D (Stages 1 & 2) | -505,185,103 | 0.75 |
| C47 | BHAP | Cooroy to Curra - Section C (Section D built) | 376,668,653 | 1.63 |
| C47 | BHAP | Cooroy to Curra - Section C (Section D not built) | 346,013,096 | 1.58 |
| C49 | NB2 | Cooroy to Curra - Section A | -124,540,496 | 0.84 |
| C50 | BHAP | Maroochydore Road Interchange Upgrade - Stages 1 & 2 | -43,642,984 | 0.79 |
| C51 | BHAP | Caloundra Road to Sunshine Motorway - Stage 4 (Stages 1 – 4) | -1,408,359,418 | 0.25 |
| C53 | BHAP | Boundary Road Interchange Upgrade | -2,788,076 | 0.97 |
| C54 | NB2 | Managed Motorways - Gateway Motorway | 370,704,869 | 2.72 |
| -- | -- | Total | -1,765,183,215 | 0.78 |
| Source: TMR 2013 | - |
|---|
| Project | Funding | Project Name | NPV ($) | BCR |
|---|---|---|---|---|
| F3 | BHAP | Meunga/Sunbeam/Lily | -26,644,493 | 0.65 |
| F4 | BHAP | Ingham to Cardwell Range Deviation | -702,502,989 | 0.11 |
| F4/F5 | BHAP | Cattle/Ingham/Cardwell | -763,858,109 | 0.18 |
| F5 | NB2 | Cattle and Frances Creek Upgrade | -109,714,804 | 0.21 |
| F6 | BHAP | Haughton River Upgrade | -397,283,384 | 0.11 |
| F8 | BHAP | Burdekin Deviation Stages 1 and 2 | -377,662,248 | 0.74 |
| F9 | NB2 | Yellow Gin Creek Upgrade | -43,725,950 | 0.09 |
| F10 | NB2 | Sandy Gully Bridge Upgrade | -70,035,637 | 0.07 |
| F11 | BHAP | Goorganga Plains Upgrade – Preserve | -304,170,956 | 0.07 |
| F12 | BHAP | Jumper Creek Upgrade | -9,116,930 0.37 | |
| F13 | NB2 | Yeppen Floodplain South Upgrade | -149,309,621 | 0.49 |
| F14 | BHAP | Currajong Creek Bridge Upgrade | -44,566,698 | 0.16 |
| F15 | BHAP | Saltwater Creek Bridge Upgrade | -38,291,244 | 0.25 |
| F16 | BHAP | Tiaro Flood Immunity Upgrades | 240,839,436 6.20 | |
| -- | -- | Total | - 1,983,825,834 | 0.49 |
| Source: TMR [2] | - |
|---|
| Project | Type | Project Name | Capital Cost ($) | Estimate Stage |
|---|---|---|---|---|
| C1 | BHAP | Cairns SAC Stage 3 – Kate St to Aumuller St | 80,000,000 | P90 |
| C3 | NB2 | Cairns SAC Stage 2 – Robert Rd to Foster Rd | 58,000,000 | P90 |
| C4 | BHAP | Edmonton to Gordonvale Duplication | 300,000,000 | P90 |
| C11 | BHAP | Townsville Northern Access – Intersections | 30,000,000 | Other |
| C13 | NB2 | MacArthur & Melton Black Drives Intersection | 26,000,000 | P50 |
| C16 | BHAP | Bowen Intersection Upgrade | 20,000,000 | Other |
| C19 | BHAP | Knobels Rd Intersection Upgrade | 5,000,000 | Planning |
| C20 | BHAP | Mackay Northern Access Upgrade - Stage 2 | 40,000,000 | Other |
| C21 | NB2 | Mackay Northern Access Upgrade | 80,000,000 | Other |
| C23 | NB2 | Mackay Intersection Upgrades Stage 2 | 9,000,000 | Other |
| C24b | BHAP | Mackay Ring Road Stage 1 Construction | 450,000,000 | Planning |
| C26 | BHAP | Hay Point Road to Mackay Duplication | 390,000,000 | Strategic |
| C27 | BHAP | Hay Point Road Intersection Upgrade | 20,000,000 | Strategic |
| C28 | BHAP | Sarina to Hay Point Road Duplication | 290,000,000 | Other |
| C29 | NB2 | Sarina Northern Access Upgrade - Coast Rd | 11,000,000 | Other |
| C30 | BHAP | Rockhampton Northern Access Upgrade - S2 | 95,000,000 | Unit Rates |
| C31 | BHAP | Rockhampton Northern Access Upgrade - S1 | 75,000,000 | Unit Rates |
| C32 | BHAP | Rockhampton Intersection upgrades | 30,000,000 | Strategic |
| C42 | BHAP | Tinana Interchange | 50,000,000 | Other |
| C43 | BHAP | Wide Bay Highway Intersection (C45 built) | 50,000,000 | Other |
| C44 | BHAP | Wide Bay Highway Intersection (C45 not built) | 110,000,000 | Other |
| C45/C46 | BHAP | Gympie Northern Approach Intersection Upgrades (Section D built) | 2,050,000,000 | Concept |
| C47 | BHAP | Cooroy to Curra - Section D (Stages 1 & 2) | 600,000,000 | Concept |
| C49 | NB2 | Cooroy to Curra - Section C (Section D built) | 790,000,000 | Concept |
| C50 | BHAP | Cooroy to Curra - Section C (Section D not built) | 209,000,000 | Unit Rates |
| C51 | BHAP | Cooroy to Curra - Section A | 1,875,000,000 | Prelim |
| C53 | BHAP | Maroochydore Road Interchange Upgrade - Stages 1 & 2 | 110,000,000 | Prelim |
| C54 | NB2 | Caloundra Road to Sunshine Motorway - Stage 4 (Stages 1 - 4) | 215,000,000 | Strategic |
| Source: TMR [27] | - |
|---|
| Project | Funding | Project Name | Capital Cost ($) | Estimate Stage |
|---|---|---|---|---|
| F3 | BHAP | Meunga/Sunbeam/Lily | 80,000,000 | Concept |
| F4 | BHAP | Ingham to Cardwell Range Deviation | 810,000,000 | PPR |
| F4/F5 | BHAP | Cattle/Ingham/Cardwell | 145,000,000 | PPR/Concept |
| F5 | NB2 | Cattle and Frances Creek Upgrade | 955,000,000 | Concept |
| F6 | BHAP | Haughton River Upgrade | 460,000,000 | Tender |
| F8 | BHAP | Burdekin Deviation Stages 1 and 2 | 1,430,000,000 | Prelim |
| F9 | NB2 | Yellow Gin Creek Upgrade | 49,000,000 | Prelim |
| F10 | NB2 | Sandy Gully Bridge Upgrade | 80,000,000 | P90 |
| F11 | BHAP | Goorganga Plains Upgrade - Preserve | 340,000,000 | PPR |
| F12 | BHAP | Jumper Creek Upgrade | 15,000,000 | Prelim |
| F13 | NB2 | Yeppen Floodplain South Upgrade | 296,000,000 | Prelim |
| F14 | BHAP | Currajong Creek Bridge Upgrade | 55,000,000 | P90 |
| F15 | BHAP | Saltwater Creek Bridge Upgrade | 52,000,000 | Strategic |
| F16 | BHAP | Tiaro Flood Immunity Upgrades | 60,000,000 | Strategic |
| Source: TMR[28] | - |
|---|
Source: TMR [2]
[1] Transport and Main Roads (2012), Bruce Highway Action Plan “Out of the Crisis”, Queensland Government
[2] Transport and Main Roads (2013), Benefit Cost Analysis – Bruce Highway Action Plan Economic Evaluation, Queensland Government, Brisbane (Unpublished)
[3] Nemhauser, G. L. and Ullmann, Z. (1969), Discrete Dynamic Programming and Capital Allocation, Management Science, 15, (9), 494-505
[4] Gear, T. E. and Cowie, G. C. (1980), A Note on Modeling Project Interdependence in Research and Development, Decision Science, 11, 738-748
[5] Fox, G. E., Baker, N. R. and Bryant, L. J. (1984), Economic Models for R&D Project Selection in the Presence of Project Interactions, Management Science, 30, 890-902
[6] Tao, X. and Schonfeld, P. (2006), Selection and Scheduling of Interdependent Transportation Projects with Island Models, Transportation Research Record: Journal of the Transportation Research Board, No. 1981, Transportation Research Board of the National Academies, Washington, D.C., 133-141
[7] Davies, W. (2012), Road Program Evaluation: Assessing the Bigger Picture, 25th ARRB Conference
[8] Transport and Main Roads (2011), Cost-benefit Analysis Manual: Road Projects, Queensland Government, Brisbane
[9] Austroads (2005), Economic Evaluation of Road Infrastructure Investment Proposals: Harmonisation of Non-Urban Road User Cost Models, Austroads, AP-R264/05
[10] Austroads (2001), Economic Evaluation of Road Investment Proposals: Improved Predictions Model for Road Crash Savings, Austroads, AP-R184
[11] Road Transport Authority (2004), Accident Reduction Guide, NSW Government
[12] Austroads (2012), Guide to Project Evaluation – Part 4: Project Evaluation Data (Updated Road User Effects Unit Values), Austroads
[13] Austroads (1996), Benefit Cost Analysis Manual, Austroads, Sydney
[14] Australian Transport Council (2006): National Guidelines for Transport Systems Management in Australia, 5 Background material, Commonwealth of Australia, Canberra
[15] Campbell, H. F. and Brown, R. P. C., (2007), Benefit-Cost Analysis Financial and Economic Appraisal Using Spreadsheets, Cambridge University Press, Cambridge
[16] Davies, W. (2011), Advanced Methods of Evaluating Benefits from Improved Flood Immunity in Queensland, Australasian Transport Research Forum 2011
[17] Transport and Main Roads (2012), Bruce Highway Upgrade (Cooroy to Curra), Queensland Government (Unpublished)
[18] Transport and Main Roads (2011), Boundary Road Interchange Upgrade, Queensland Government
[19] Transport and Main Roads (2012), Bruce Highway Action Plan – Project Descriptions, Queensland Government (Unpublished)
[20] Transport and Main Roads (2010), National Managed Motorways Discussion Paper, Queensland Government (Unpublished)
[21] VIASTRADA (2008), SIDRA Solutions, VIASTRADA LTD, available at http://viastrada.co.nz, accessed 27/05/2013
[22] Department of Infrastructure and Transport (2013), Intelligent Transport Systems, Australian Government, available at www.infrastructure.gov.au, accessed 27/05/2013
[23] Transport and Main Roads (2012), Bruce Widening, Queensland Government, Brisbane (Unpublished)
[24] Department of Infrastructure and Transport (2013), A Ten Year Plan for a Better, Safer Bruce Highway, Australian Government
[25] Transport and Main Roads (2012), Project Cost Estimating Manual Fifth Edition, Queensland Government
[26] Miller, E. M. (2005), The Cutoff Benefit-Cost Ratio Should Exceed One.: An article from:
Engineering Economist, Institute of Industrial Engineers.
[27] Transport and Main Roads (2012), Capacity Projects – 20120829, Queensland Government (Unpublished Spreadsheet)
[28] Transport and Main Roads (2012), Flooding Projects – 20120829, Queensland Government (Unpublished Spreadsheet)