20210712 Bungalow construction (trenches) - day 6

Words
90
Reading
1 min
5y
Listen to this post
~1 min

The crew starts digging trenches for the foundations following the wooden pentagons that were prepared last week. The termite control crew is here too. They will spray anti-termite product on the earth at the bottom of the trenches before the foundations are made.
IMG_7171.jpg
IMG_7170.jpg

Cement delivered.
IMG_7182.jpg

Crew toilet in progress. It's just a private hole in the ground right now...
IMG_7167.jpg
IMG_7177.jpg
IMG_7178.jpg

Adi made himself a new tool to verify angles of pentagons.
IMG_7179.jpg
IMG_7180.jpg

Installed new triangular shade in the Hut.
IMG_7175.jpg

Meanwhile at the warehouse metal connectors for the steel beams are being fabricated