20210906 Bungalow construction (slab concrete pour) - day 62

Today is the largest concrete pour of the project. The past 6 weeks have been leading up to this.

The entire main floor, a 12 cm thick slab of about 150 square meters is being poured in one go.

The set up is similar to the last pour...
IMG_8459.jpg
IMG_8460.jpg

... but the ramp starts higher and is longer this time around since there is more ground to cover.
IMG_8461.jpg
IMG_8462.jpg

The bedroom area is poured first
IMG_8463.jpg

Liquid concrete arrives at the bottom of the ramp and is distributed evenly around the entire area manually.
IMG_8465.jpg
IMG_8466.jpg

IMG_8469.jpg

IMG_8470.jpg

The long horizontal bar is the limit between inside and outside the bedroom. Once the concrete is cured the metal is removed leaving a 3cm step to prevent rain water from coming in.
IMG_8471.jpg

A corner of the floating slab.
IMG_8479.jpg

Spacer keeps the two horizontal grids apart.
IMG_8480.jpg

One of the five 108 degree angles of the bedroom pentagon.
IMG_8481.jpg

Finishing up around 6pm.