Houses - 9
The installation of the window will start from December 12th. My house has a fairly large curtain wall window. As I mentioned a while ago, the window is so important that it takes about 1/10 of the cost of the construction work. It would be important for the South to have a lot of windows and the north to have as few windows as possible.
Because PVC is cheap and insulation performance is much better, it is used a lot, but it is a little in shape, and the curtain wall window
Stiffness? So I can only use aluminum. The system windows are not doubled, but usually one.
Unlike ordinary windows, it is very closed when it is closed and the frame itself is very designed for insulation / air tightness.
There is more effect than normal window two. It looks good and has good performance. Of course it is much more expensive.
After installing the window, the glass specification is also important to put the glass on the window.
Whether it is double or triple, whether it is filled with argon gas or low-e coating.
Please do not spare money in the window.
The woodworking work started on December 17th. It's the second floor. That way, the frame is cut into pieces, and a gypsum board is placed on top of it.
In this way, besides the framing, most of the places where the shape appears in the house are finished with wood and woodwork. You know how important it is. In this way, it gradually finishes.
Woodworking construction is going up to the first floor after attic, 2nd floor. The largest living room wall was also worked that way.
In early January, we will visit the Gangnam / Pangyo area to find tiles / floors. ㅠ,. ㅠ It is a sadness of the local age.
The floor, floor 1, 2 floor solid wood flooring, attic flooring Ondol flooring, and the specs of the original specifications at the time of the quote went up a lot more .. Prices are up
I saw a lot of knots and selected a floor that gives a calm feeling of naturalness and a little dark color.
As soon as I saw my wife and me at the floor, I felt it at the same time, so I chose that one.
It is not too black and not too white. The species is orc. (In fact, most of the floors are orc.)
Tile picking is .. really .. ha ... It is too hard. It seems that there is one more thing to write even if you write only tile.
I visited three major companies in Kangnam, Pangyo, and picked them, picked them, picked them, picked ten kinds of tiles
I also think the price. It is a task that should be and is too tough.
There was a process of decision which was not possible during the construction of the housing, but it can be said that tile selection was the most difficult. ㅠ
January 24th .. I have been working on a carpenter for over a month and it is still going on. ㅠ
The lower cabin under the stairs was carried out by a woodworker, not furniture.
I keep covering like this. Now it looks like a house.
I will write on the next page, but it is a task to install a switch called Jung, which was really annoying during the woodworking process.
I really suffered, but I suffered a lot because of that.
February 12th .. Woodwork construction still in progress .. ;; 2 months ago
In the meantime, we start working on the tiles. I did not like the quality of the tiles at the end and there was a slight argument with the field director. ㅠ
I can not do it and I can not open it. I can not let the worker try to work with the sample in advance. It is really hard.
February 15 .. Finally, the long and long woodworking work is finally finished and work begins.
It's putty, exactly. The parts to be roughened are handled differently and the part to be painted is the surface smoothness is most important.
It is the process of getting smoothness through what is called putty in that way.
Putty work is the main reason paint is more expensive than paint. I do putty work like that once and then change everything and then change again and again.
I will do it again for a few days. If you do that, the whole wall will be covered with putty.
This is just a putty operation, not a painted job. I have to go back and forth a few times,
The surface of the gypsum board is so neatly trimmed.
A full-scale painting work will begin around March 1. The common area is painted, the room is wallpapered, and the AV room is painted specially. haha
All the colors are white, the points are only gray, and the AV room is black. I did not want expensive green paint and wanted green paint of Samhwa paint. Picking a paint color table and choosing a paint color was a painstaking task. ㅠ
In this way, the first floor basin space is gray on the inside and white on the outside. Work is done
March 11 Lighting, electrical work begins. I also have a sealing fan.
Sealing fans have been written before, but if you are a space, I strongly recommend it. I eat less electricity and it's too cool
The cost of heating / cooling is also very good. Good design.
All the lights in the whole house are LED. If you have a high ceiling, it will be difficult to replace it. LED lighting is said to go on for 5 to 10 years.
However, the ballast can go frequently, so we only removed the ballast where it is easy to replace. -> This part is difficult for the electric boss.
After the lighting work, I keep the LED lights on for a few days. Because it is to determine the initial failure.
In fact, there are those who go out in a day or two. However, the children who passed this stage are said to be quite long.
Indirect lighting and line lighting were applied to the house quite a lot. T5 is also made to order according to the length, so I took care of lighting.
The lighting color is warm to 3500k.
It is the window of the stair climbing place. It's pretty big. I tried to make that part a regular window, but it stuck right next door. I can not see it outside next door.
I applied it as a glass block in my opinion. The cost of the construction was inconvenient. ㅠ However, I am satisfied when I see it later.
It is wonderful when the light shakes in. I can not see the neighbor next door.
The exterior work also starts a little bit. My house has a brick tile finish on the outside.
There are places where you can get bored with Cheonggo brick, but there are three places in the exterior that give you the point as a whiskey.
Sorry. I would like to increase the number of times, and then I will go up to the exterior work and finish. ㅠ ㅠ Even if I try to reduce it, it keeps growing.
I guess I can not be any more. I will finish it as soon as possible.