20210918 Bungalow construction (gutter concrete) - day 74

Words
142
Reading
1 min
5y
Listen to this post
~1 min

In parallel with the installation of the metal structures the gutter in front of the property is being created.
IMG_8648.jpg
IMG_8649.jpg

It's intense work that requires about 15 workers to act in concert.
IMG_8650.jpg
IMG_8651.jpg

Some installing the formwork...
IMG_8661.jpg
IMG_8662.jpg

... while another crew feeds the concrete mixer...
IMG_8679.jpg
IMG_8682.jpg
IMG_8683.jpg

... and pouring the concrete mix in the formwork to create walls and bottom of the U-shaped gutter.
IMG_8685.jpg
IMG_8686.jpg
IMG_8687.jpg

The gutter is made in several tiers. This part is drying...
IMG_8706a.jpg
IMG_8707.jpg

... while other parts are being poured.
IMG_8715.jpg
IMG_8725.jpg
IMG_8727.jpg
IMG_8728.jpg
IMG_8730.jpg

Andi and I help the workers define the exact placement and angles of the access ramp.
IMG_8722.jpg
IMG_8724.jpg

...for the future entrance
IMG_8733a.jpg

Rainwater from last night needs to be pumped-out so it doesn't corrupt the concrete.
IMG_8729.jpg

The west wall of the gutter also serves as retaining wall for the land. Part of the wall is drying while the other part is waiting for more concrete
IMG_8731.jpg
IMG_8732.jpg