20210831 Bungalow construction (beams formwork) - day 56

Words
131
Reading
1 min
Listen
Play
5y

Formwork for the beams that will support the concrete slab above the workshop.
IMG_8260.jpg
IMG_8261.jpg

In the center of this photo you can see the bathroom walls and the opening for the door.
IMG_8262.jpg

All the beams converge on top of the pentagonal column in the center of the workshop.
IMG_8263.jpg
IMG_8264.jpg

View from above.
IMG_8249.jpg
IMG_8250.jpg

Workshop entrance.
IMG_8265.jpg
IMG_8266.jpg

Rafters are being painted.
IMG_8256.jpg

This grey is too cold. We're going to look for a warmer vibe.
IMG_8251.jpg
IMG_8253.jpg
IMG_8254.jpg

Fabricating the formwork for the concrete beams that link the enclosed volume to the external row of columns.
IMG_8257.jpg

The external row of columns is 130cm from the walls.
IMG_8258.jpg
IMG_8259.jpg

The slab will extend beyond this row of columns. The peripheral terrace outside the main living space will be between 190cm and 270cm wide depending on which side of the pentagon it is located.