20210827 Bungalow construction (formwork removed) - day 52

Words
221
Reading
1 min
Listen
Play
5y

The formwork of the concrete pour from 2 days ago has been removed. Brick walls have been added to extend concrete walls where scheduled.

Recessed space for the rainwater evacuation system in the corridor that leads to the workshop.
IMG_8179.jpg

In one instance the formwork has moved during the pour. It has created a concrete bulge at the bottom of this wall. This photo doesn't really capture it but it is a displacement of several centimeters.
IMG_8181.jpg
IMG_8187.jpg

You see the shadow of the bulge here. We will triple check formwork before future pours.
IMG_8184.jpg

All the other walls look great.
IMG_8182.jpg
IMG_8183.jpg
IMG_8189.jpg

This will be the workbench at 90cm high. It is scheduled to be covered with a couple layers of 18mm plywood.
IMG_8185.jpg
IMG_8186.jpg

There were a few misalignments in the formwork of the columns. This one is kinda playful. A happy accident.
IMG_8190.jpg
IMG_8191.jpg

This one is less interesting but is outside and will be hidden behind the trimdek (undulated metal) skin.
IMG_8194.jpg

Overall this pour was a success.
IMG_8193.jpg
IMG_8195.jpg
IMG_8196.jpg

Formwork for the pentagonal column at the centre of the workshop is ready.
IMG_8178.jpg
IMG_8180.jpg

Concept drawing for the pentagonal column formwork.
20210822PentagonalColumnForm.w.jpg

Adi holds the pentagonal shape of the column which served as a guide to create the formwork.
IMG_8199.jpg

Some of the earth from the excavation of the workshop is brought to another part of the garden to fill old irrigation canals.
IMG_8197.jpg
IMG_8200.jpg