  1. Location: Greenfield coastal location outside the port of Safi (200km south of Casablanca)
  2. Capacity : 1,380MW (gross)
  3. Type : Coal-fired power plant
  4. Major equipment : Boilers from IHI and steam turbines from Hitachi

Source: http://www.pfie.com/ultra-supercritical-project-financing/21177365.fullarticle