  1. Location : Near the city of Kirikkale, 50km east of Ankara
  2. Combined-cycle power plant comprising two Alstom gas turbines and one steam turbine
  3. Gross output capacity of up to 950MW
  4. Financial close : December 2014
  5. In operation : around mid-2017

Source : http://www.pfie.com/singin-in-the-rain/21177837.fullarticle