Houses 8
For the housing construction, you can think about 3 ~ 5 months for wooden and 4 ~ 6 months for concrete.
Of course, I took just over seven months, and the construction period can vary due to these and other circumstances.
Sometimes it is completed in less than 3 months. Sometimes it takes longer because of financial problems or weather problems ~
Because of the weather problem, we usually aim to start in spring or in the summer when the rainy season is over and finish before winter.
I decided to complete the construction in the spring of next year because the construction started at the end of September, and contracted for a total of 7 months.
It is necessary to make winter during construction, but it is necessary to have proper temperature to harden the concrete.
In winter, we will go through the woodworking work, etc., and finish it by finishing the exterior in spring.
Land surveying was completed in mid-September with a construction contract. It's the job of knowing exactly where the boundaries of my land are.
If the boundary of my land is correct, I will build a house based on the reference to the plan.
Also at the end of last year of last year, there is Chuseok, so if you cut it off during construction,
We will start construction on September 27th after Chuseok has finished.
It is a scene of setting up a canonical frame based on the September 27 surveying point. You can think of it as a boundary-work where the building is located on the ground based on the design.
September 28 will be the first time. Usually, this time, we sprinkle some makgeolli, and the family takes a shovel together with the first shovel and takes a picture.
Start digging right into the forklift! Why are you digging the land for building a house? The house is not just on the ground. I made a structure called base and on top of it
The structure is going up. When we build all the houses, we have to dig the land like this.
We dig the ground on September 29, lay gravel on it, lay vinyl on it, and throw away concrete. You can see that the work is done on the flat concrete surface in order to get the precise positioning of the foundations. The euphemism is positioned by the ship, and when it bounces,
On September 30, feeding is completed. Foundation work will start based on that fried food.
On Oct. 1, we set up a mold for the foundation on the basis of the eavesdropping, and place the reinforcement on it. This is called a line base.
I usually use a lot of base mat bases, but I do not think I need to use them here. The line basics are a little more expensive.
On October 8, the line foundation was completed. You can see that there are concrete walls on the foundation.
Waterproofing works and extrusion methods are installed around the foundation, and installation of sewage / sewage pipes to run under the house is also carried out.
Those are the sewers that come down from the second floor or those that connect to the toilet on the first floor.
I can not see well, but the electric works are going on as well. Do you see the black pipe far away?
On October 10, we fill up the part that we digged with dirt, cover the insulation again, and pipe the reinforcing steel on it.
If you look at the left side, the floating faucet used in the yard is also installed.
October 12th ..
The floor is already covered with concrete, the electrical piping work is finished, and even it is going up to the form of the first floor wall.
Is it really fast? I do not know why it took so long to do so fast.
Yellow wire is blue, communication line red is TV line, etc.
I did not care about the electrical work, but the induction is 7kW, so I only care about connecting the line to one leakage breaker.
I was worried about putting the TV in the future.
October 18th .. 1st floor wall formwork, rebar laying work is over and we are working on the second floor floor plywood. Pour the concrete until the second floor floor frame is finished. The second floor is more complicated than I thought? There are quite a lot of different parts of the height, and the room was also a little difficult because I had to go up three stairs and the height varied.
On October 22, we put concrete on the 2nd floor and 1st floor walls. You wonder how the electric wires in my house go through?
In that way, a tube called CD tube is buried in the wall. There are various wires, internet lines and so on. Before we make the wall, we all wire through the tube like that. Sometimes thicker pipes are used for thicker lines.
On October 30th, two-story walls are also under construction in this way.
The floor structure of the 2nd to 3rd floors was also complicated, so we could see that the ball was quite crowded in the field.
The day of November 12 is cold. The framing should end soon .. Now it's almost over. I'm working on the last roof part.
That kind of gauntlet was a unique work. I can not cover the mold in advance.
About November 20 .. The construction of the frame was finally completed. It is the way of looking up attic from living room.
The quality of the framing seemed to be good even when I was a beginner. Even if you measure in each room, only 1cm difference from the schematic.
More amazing than thought .. ;; It was finished with quality.
There will be a lot of things going on here and there.
Internal metal works will start on November 22. The inner staircase was made entirely of steel plates folded and welded
All of the unique spaces in the above living room photographs are all made through the inside of the hardware.
Metal construction was quite successful, and I had a lot of twists and turns as I modified the parts that did not work well. ㅠ
November 29th It is the metal work of space which divides the second floor and attic and living room.
That's it.
I do not know how many times I made it for the part construction and came down from Seoul.
That metal work ... will continue until the end of December. This metal work and built-in woodworking work took quite a while.
On December 8th, the boiler piping is done on the floor and the pipeline is broken. Because the weather was already getting cold, I closed all the windows.
I set the room temperature by blowing hot air.