From the middle of February to the end of the second half, the weather was gradually released and now it is time to start the exterior work.
In fact, while the outside work was done, the inside work continued until the end of the construction. I will share the story with you.
February 13 A brick tile sample arrives and we are in the middle of sightseeing. The reason why we made brick tiles (folded bricks) instead of bricks outdoors is because we used thick insulation. Chuncheon is the coldest region in Korea
The thickness of the above insulation is applied. However, my house can be set as a previous standard when I get a building permit. But I was a bit greedy and considered 190mm. 190mm, the house itself is a lot bigger, because it is based on the center line, the internal area is also slightly damaged (see Cima's comment). It is also hard to use hardware to fix the brick on the outer wall of the insulation. And because tiles are cheaper than bricks, I decided to make tiles in the end.
After seeing various rendering results and visiting other houses (Pangyo, Kim, etc.)
It is a sample of blue stone brick-style wave wall stone. Actually, I did not know when I put it like that.
Eventually, we make decisions based on the opinions of the architects. (I liked the yellow / red brick line, and the architectural office recommended white brick
Wife liked bronze brick.)
I felt cold at the end of February. I decided to put off some insulation work and decided to continue the construction work.
I made the door not the ready-made (but it's not particularly good) and painted it in white without a pattern.
My house has no moldings at all. I just gave a gap between the mold and the wall where the molding was supposed to be.
That gap is on the ceiling wall of our house. It's not my opinion, but it's decided by the architectural office. It is more beautiful than molding ~~
The construction is also more difficult.
Overall paint quality is very good. The president who came to do the furniture work later enough to admire
There are a lot of metal works from time to time outside the house, but I will skip this part.
The outside of the house gave me three points in this way. There were many twists and turns in the front door.
I think that the frame is wrong and I want to recreate it .. I am also worried about how to design the door.
Let's not be like a door.
So this is the final door design.
Actually, at first, a homecoming uncle .. Visitor can not find the door .. There are many times when I come back to the living room door.
Now everyone has adapted
The grass is dirty and messy. ㅠ It is difficult to cut in flat.
At the end of February .. The temperature is rising to the image and the external insulation is sticking.
This is actually the most stressed part of the construction because there are not many pictures.
I also fought with the chief, pulled out the construction worker once, and for a week, at the end of the discussion with the architect's office, the field chief,
I made some compromise and proceeded to construct.
I would like to write this part in detail, but it is too complicated.
Temperature during bonding of insulation, mixing of adhesive materials, problems of under extrusion / bead method, etc.
I finally found the LH specification and I pushed it in front of my nose and eventually proceeded my way.
If you look at it now, you can see the photo.
I used to write about this problem in my family once before.
They should have gone through the cold of Chuncheon directly.
Anyway ... Finally, after the insulation is finished, it will be put on top of it with mortar and put the tile on it.
By the end of March, we will finally start building brick tiles (brick tiles). Since the brick color is fixed, you have to set the color to put in between.
I will make a decision after applying the sample as above. When it was wet, I had to pick it again after it dried.
As it is a high brick (st), I can appreciate that there are many different colors.
So, after all, I took all those bricks and put them back on.
The red bricks are torn out and under construction. The dark ones are wet bricks because of the rain at the time.
At the same time, inside the AV room lighting and speaker construction .. To accommodate Dolby atmos, four 8-inch ceiling speakers have been embedded in the ceiling. There is no lighting or electricity in that part, but the electric boss has helped me a lot. Why is it so difficult to pull out the grill?
This is the lighting of the attic. From the woodworker, I made a gap like that and made a line LED light that I made after I finished the work.
I was so proud of you. ㅠ
Exterior brick construction is almost finished, lighting construction is almost finished ..
All three points gave me points with line lighting. It's pretty, but it's so bright that it's a bit dark.
It is a little unfortunate that it would be great if you become a point.
Already in mid-April .. Flooring is under construction. The first floor is a wide dark oak timber floor
The second floor has bright oak timber flooring, and the loft oak flooring. I wrote about the floor in my pores, but later
I'll show you.
April 18 .. The internal primary cleaning was completed and the outside scaffolding (ashiba) was also dismantled.
It is the first time I saw the shape of the house properly. ㅠ. ㅠ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ ㅋ
From April 19, furniture construction will begin. After finishing 80% construction for 2 days, the rest came back to the finish point and handed it to me.
The furniture boss was very interested in AV and helped us install the screen. ㅎㅎ I tried to be alone and I was arrogant ㅠ
Furniture construction is also a very crucial step in determining the design and function of your home. You have to hold up to 1/10 of the cost of the construction work.
The most expensive of these is the kitchen furniture. The price of the faucet and the top plate is not enough, and the furniture door is very expensive if you paint it.
We installed Chinese doors on April 26th. I installed it in a place called Weed Jig. I do not know if you look at the pictures ...
The height is 2700 so it is huge. I have a bit of power when I open it. ㅠ But it's like soft closing function.
Weed in the middle of the gypsum, while in the bathroom room, we went together at the Weed.
This Chinese language is actually changed several times, the specifications are changed and the way is changed, so it is only one month in Chinese language.
Originally made in-house, but I took a little more money in Weed Jisu.
We went to the Seoul exhibition hall at Weed Jisseong to see the materials, design, glass type, and later decided to reshape the design again.