From: Emad Hanna
To: Jeffrey Epstein [email protected]
Date: Sep 24, 2010 12:50 PM

Jeffrey,

I received a request from Gary to process requisition #6 for Big Bear Construction for the Mechanical Desal Concrete Formwork in the amount of $ 109,288.

Including this payment we would paid $ 459,766.75 and would have remaining $ 366,529.25 to complete this phase of the project.

Requesting approval to process payment.

Thank you

Emad Hanna

Project Controller