From: Emad Hanna
To: Jeffrey Epstein [email protected]
Date: Jun 4, 2010 7:37 PM
Jeffrey,
Gary is requesting I get a quick approval from you to process the attached payment of $ 114,665 for the concrete contract $ 821,461 for the Mechanical Desal for progress work for a crew of 12 for onsite work.
The total payments made so far is $ 112,931.25
Thank you
Emad Hanna
Project Controller
HBRK Associates
PO Box 400
New York, NY 10150
Ph
Fax