From: Emad Hanna
To: Jeffrey Epstein <Ueevacationagmail.comj>
Date: Jul 27, 2009 3:34 PM
Jeffrey,
I just wanted you to be informed of the following:
Gary Kerney has approved a payment of $ 9,241 to Kraus Manning for testing on the mechanical building.
This puts this budget line item over budget by $ 7,771 and Gary also stated there will be an additional $ 12,009 of testing fees.
So he is adding a change order for S 19,771 bringing the total amount for testing to S 29,771.
If you're ok with all the above I will process this payment and adjust the working budget for the change order.
Thank you
Emad Hanna
Project Controller
HBRK Associates
PO Box 400
New York, NY 10150
Ph █████████████