Two of the main purposes of building a house/shelter are staying warm and dry. Out ancestors knew how to do this without the need of industrially produced material, mainly by organizing natural fibers and minerals in ways that were effective for the task. However, we didn't inherit this knowledge as much as we would like to learn such skills, we also want to have a place that can ease up the harshness of south Chilean winter... before winter arrives.

So, we've had to buy the usual roofing materials for low budget houses, such as OSB panels, pine wood structural beams, and zinc plates. The floor will be more in tune with the natural materials we enjoy, but we'll get there soon enough.

At the time of starting the roof we had many doubts, many ideas too. @choli's thought was the saying: the devil knows more because he is old than because he is a devil haha ​​​​😅 our close friends recommended a level and uniform roof so that we did not have problems with the rains, since we are a little close before these rains begin and there had to be a solution at the moment.

Anyway, after the discussion about which materials to use we had to see that we proper leveling for the roof, to prevent leaks in the future. We tried leveling by adding a some pieces of wood, which we marked with a line after using the transparent hose method.

img_0.5587456895791263.jpg

If you're not familiar with water leveling then take a look at this video, though you can do it with only a hose and avoid the fancy gadgets this guy uses:

A lot of effort was needed to do the marks, and even more to get a picture where both of us worked on this 😅

img_0.46749526745207964.jpg

Here is an added branch with the mark on where the level should be:

img_0.17143742688677027.jpg

We were trying out this system when @choli 's father arrived to give us a hand, also bringing us some materials we bought. Now having straight beams we were able to see how - unstraight - everything was, and he decided that it was better to lower the pillars to level with the lowest of them.

img_0.1163385596805287.jpg

@choli 's father is experienced in building so he had a very different perspective which gave our build a lot of sturdiness.

Here with the face of not helping much, but something is something.

Already with the trusses installed, with the help of @choli's father, and starting the first pitches. Us being the juniors delivering materials.

img_0.5677936103538079.jpg

The roof was put together quickly, though we still need to place de zinc plates. However, with the OSB it already stays pretty dry inside and offers some protection from the light summer rains.

While we wait for the expert to come and help us again, we've moved on to advancing with the floor. We already did a post on what we were planning so if you're interested in the design, go check it out

img_0.8361945680622405.jpg

The first layer is gravel and then comes a plastic cover to stop the moisture from rising. At the same time the gravel will encourage moisture to go down so we should have a nice and dry floor. The plastic goes on both sides but we took this picture to show you the overall idea. In this picture you can notice we added a few more pillars to the structure which made it way more solid

img_0.17746805405440813.jpg

The next layer is road base, which is a mixture of different sizes of stones, with clay and sand, it varies depending on the area. This layer serves as stability and firmness to what is going to be our floor.

img_0.04472748994231335.jpg

We begin adding the road base which has meant endless amounts of shoveling and transporting with the cartwheel. We're going to end up with a lot of muscle after this build 💪

img_0.9719335154425055.jpg

We had to improvise a rammer, so that the layer does not come loose. It works very well 👌

img_0.727007464830159.jpg

And there we have the first part of this layer laid out. We still have more material so we want to put it all here.